# Do I need a party wall agreement? Notices, awards and surveyors explained

When the Party Wall etc. Act 1996 applies, which notice to serve and when, what happens if your neighbour doesn't reply, and agreed vs two surveyors.

[All guides](https://www.rosecrestgroupltd.co.uk/guides.md)

If you're building on or near a wall you share with a neighbour, the Party Wall etc. Act 1996 probably applies. What people call a "party wall agreement" is usually one of two things: the neighbour's written consent to your notice, or a party wall award made by surveyors.

## Work that usually needs a notice

-   Work to a party wall itself, such as cutting into it to insert beams for a loft conversion or extension, raising it, or underpinning it.
-   Building a new wall on or at the boundary line.
-   Excavating within 3 metres of a neighbouring building and deeper than its foundations, or within 6 metres for some deeper excavations.

## Which notice, and how much warning

Party wall notice periods

| Notice | Typical work | Minimum notice |
| --- | --- | --- |
| Party structure notice | Work to an existing party wall | 2 months |
| Line of junction notice | A new wall on or at the boundary | 1 month |
| Notice of adjacent excavation | Excavating near a neighbouring building | 1 month |

## What happens after you serve notice

Your neighbour (the adjoining owner) can consent in writing or dissent. If they don't respond within 14 days, a dispute is treated as having arisen.

A dispute doesn't mean a falling-out. It means surveyors are appointed to settle how the work is done in a party wall award, commonly misnamed the party wall agreement.

## Agreed surveyor or two surveyors?

Party wall surveyor appointments compared

|  | Agreed surveyor | Two surveyors |
| --- | --- | --- |
| Who acts | One impartial surveyor acts for both owners | Each owner appoints their own surveyor |
| When it's used | Both owners consent to sharing a surveyor | Either owner has concerns about impartiality |
| If they disagree | Not applicable | The two surveyors select a third surveyor, who is only called on if they can't agree |

Either way, the surveyors' work includes site visits, a schedule of condition recording the neighbouring property before work starts, and drafting the award.

## How long it takes

Straightforward cases can finish in a few weeks. Where an award is needed it typically takes 6–8 weeks, so serve notice well before you plan to start.

## Serving the notice yourself

You can serve a notice yourself. Our free party wall notice generator produces one from your details, or we can prepare and serve notices for you.

## Related

-   [Party wall surveyor](https://www.rosecrestgroupltd.co.uk/services/party-wall.md)
-   [Free party wall notice generator](https://www.rosecrestgroupltd.co.uk/services/party-wall/notice-generator.md)
-   [Starting work without a party wall agreement](https://www.rosecrestgroupltd.co.uk/blog/start-building-without-party-wall-agreement.md)
-   [The Party Wall Act 1996 explained](https://www.rosecrestgroupltd.co.uk/blog/ultimate-guide-party-wall-act-1996.md)

[Request an inspection](https://www.rosecrestgroupltd.co.uk/request-inspection.md)

## Frequently asked questions

###

Serving notice is a legal requirement for work covered by the Party Wall etc. Act 1996. After notice, the outcome is either your neighbour's written consent or a party wall award prepared by surveyors.

###

If the adjoining owner doesn't respond within 14 days, a dispute is treated as having arisen and surveyors are appointed to prepare a party wall award.

###

Yes, as an Agreed Surveyor, provided both owners consent. Where one owner has concerns about impartiality, each appoints their own surveyor.

###

Where an award is needed it typically takes 6–8 weeks, though this varies with the works and how the adjoining owner responds.

---

## Contact Rosecrest Group Ltd

- Request an inspection: https://www.rosecrestgroupltd.co.uk/request-inspection.md
- Phone: 020 4576 5317
- Email: rge@rosecrestgroupltd.co.uk
- Site index for AI systems: https://www.rosecrestgroupltd.co.uk/llms.txt