If you're building on or near a wall you share with a neighbour, the Party Wall etc. Act 1996 probably applies. What people call a "party wall agreement" is usually one of two things: the neighbour's written consent to your notice, or a party wall award made by surveyors.

Work that usually needs a notice

  • Work to a party wall itself, such as cutting into it to insert beams for a loft conversion or extension, raising it, or underpinning it.
  • Building a new wall on or at the boundary line.
  • Excavating within 3 metres of a neighbouring building and deeper than its foundations, or within 6 metres for some deeper excavations.

Which notice, and how much warning

Party wall notice periods
NoticeTypical workMinimum notice
Party structure noticeWork to an existing party wall2 months
Line of junction noticeA new wall on or at the boundary1 month
Notice of adjacent excavationExcavating near a neighbouring building1 month

What happens after you serve notice

Your neighbour (the adjoining owner) can consent in writing or dissent. If they don't respond within 14 days, a dispute is treated as having arisen.

A dispute doesn't mean a falling-out. It means surveyors are appointed to settle how the work is done in a party wall award, commonly misnamed the party wall agreement.

Agreed surveyor or two surveyors?

Party wall surveyor appointments compared
Agreed surveyorTwo surveyors
Who actsOne impartial surveyor acts for both ownersEach owner appoints their own surveyor
When it's usedBoth owners consent to sharing a surveyorEither owner has concerns about impartiality
If they disagreeNot applicableThe two surveyors select a third surveyor, who is only called on if they can't agree

Either way, the surveyors' work includes site visits, a schedule of condition recording the neighbouring property before work starts, and drafting the award.

How long it takes

Straightforward cases can finish in a few weeks. Where an award is needed it typically takes 6–8 weeks, so serve notice well before you plan to start.

Serving the notice yourself

You can serve a notice yourself. Our free party wall notice generator produces one from your details, or we can prepare and serve notices for you.